Friday, February 09, 2007
No room to sleep
The vanity for the girls' bath arrived yesterday but it's so heavy it has to stay in the garage until some man with muscles can help me negotiate it upstairs. FedEx also dropped off the faucet for the girls' bath and the fixture store called to say they have the closet door knob ready to be picked up. That means we have everything for that bath except the countertop and we can only order that when we've mounted the vanity. I could do that this weekend but we would be without a sink in that room for at least two weeks until the countertop is installed and we've connected the sink and faucet. I'm not sure whether that's a good idea or not.
Wednesday, February 07, 2007
Knobs
Ah, door knobs. Functional and decorative and the quickest and easiest way to give your interior a whole new look. Ha, that piece of advice comes from some design show or HGTV website. That's cyber reality.
In the real world, where I live, changing a door knob is frustrating, time-consuming and very, very expensive.
In this house all the public spaces have Schlage teak trimmed knobs, very 70s but also tasteful and they match the doors. They are staying. The closets and the front door have pewter handles from Arrow. Also gorgeous, and we will not be replacing these either. But the private spaces, bedroom and some bathroom doors have porcelain or granite knobs and these have to go.
In bizarro universe I'd just pull/unscrew the offending part off the door, trot down to the local hardware store and buy some sexy replacements. In my world, I discover that no one makes decorative trims for Schlage knobs so I have to buy a whole new knob. As a temporary solution I settle on pulling the offending pink granite trim off the bathroom door and swapping it with the trim from the basement door. The basement is now looking a little funky but who's going to notice?
Then I try to replace the above knob in matching pink granite but it requires an allen key in a size I don't possess. A quick trip to the local hardware store and $1.29+tax buys me a set of allen keys, one of which is the correct size. (This turns out to be the bargain of the week).
Armed with the offending door knob and original manufacturer's name (Arrow) I head off, at the hardware store owner's suggestion, to the local locksmith. He looks at it, declares he doesn't understand how it works, but can sell me an absolutely hideous shiny brass and glass knob in a vaguely Victorian look at a reasonable price that may work. I decline and he suggests I visit the local fancy decorative hardware store where he assures me I'll find something more my taste but "it's going to cost you".
And the local expensive store? I show the guy all the bits and he finds a manufacturer he swears is going to have a knob to fit, even though he doesn't understand how it works either. I pick out one small knob to replace the above monstrosity and two larger ones to take the place of the flowery porcelain powder room handle. Then he totals it all up for me, three knobs plus plates = $257. These had better work, I have my doubts as the knobs screw onto the spindles and I don't see how the replacements are going to do that but I'll bow to the salesman's superior knowledge.
But good grief, $257 just to get rid of a little hideous. Imagine if I had to replace every door knob in the house. Especially when I really want these beauties from
Turnstyle Designs which I believe run about $450 each.
Tuesday, February 06, 2007
House Art
It might be 7 below zero but I can't wait to install my lovely new mailbox that arrived yesterday. houseArt's slogan is: Finally, mailboxes you can love. And I do.
Now I have to find a post I don't hate......
Monday, February 05, 2007
Bathroom Race
Porcelanosa called today to say the tiles are in for the boys' bath, then I got a call to say the vanity I bought on ebay for the girls' bath had shipped and I put two coats of Benjamin Moore Cotton Balls on the girls' bath walls. In an attempt to stop spending money I also soaked the shower head in Oxy Clean until it actually delivered a decent flow of water. I was surprised at the weight of the shower head when I unscrewed it, in fact I almost dropped it. If that had happened it would probably have gone right through the bath and then we would have had to replace that and of course all the tiles too.
It could so easily have been a very expensive remodel after all.
Saturday, February 03, 2007
Serious Ugly Revisited
Just as I'm getting rid of the fugly 1970 avocado green/pink combo in the girls' bathroom, HGTV's Design on a Dime has a great new idea for a "Pretty in Pink" bedroom using complimentary colors.
Either I'm behind the curve or have no taste because it still screams UGLY to me.
Thursday, February 01, 2007
Extreme surgery needed
Will someone please help me? I think I need to enter rehab.
My problem?
I started in a small way, ordering music and books from Amazon, then computers from Dell and Apple. For a long time I was happy and then we started this remodeling project and things have gotten out of control. First I bought a sink online, then I progressed to faucets, showers and accessories, including a toilet seat.
I thought I could manage my habit, after all it was just one bathroom, a finite project. Then I started buying for the second bathroom, one we had no plan to undertake in the foreseeable future. But it was so easy, things were cheaper and readily available online. Just a couple of clicks, totally painless. So I ordered a vanity, and another faucet and I can justify it because it's a small project that will be easy to complete.
And then the madness began. I was searching for a door knob to replace the hideous pink stone one in the girls bath when I came across something I've lusted after ever since we moved here. A bronze mailbox, contemporary in style that reflects the design of the house. But it wasn't in the budget until we re-tarmac the drive. (Ironically we missed out in the great mailbox vandalism episode that struck the village last May when most of out neighbors got a new mailbox courtesy of the idiot who smashed them with a bat and was caught by the village police. End of term madness, almost as expensive as remodeling).
Today though, I was having no luck with the door knobs but one little weblink and I found my object of desire. Instantly available, it was perfect; it even looks like our roof line. And two clicks later I had ordered the Da Vinci mailbox.
I'm sure I'm going to love it when it arrives, but right now I'm feeling a little sick. I will have to buy a new post and dig out the old one and concrete in a new one in a new position. More tasks and btw it's February and the ground is frozen. Crazy woman with bad credit card habit.
Plus I still haven't replaced this beauty.
Help, I need help, either the credit card or the internet will have to be cut off.
Tuesday, January 30, 2007
This is "gentle" remodeling
Steve agreed with me that the white ceramic vessel sink I ordered would look even better in the girls' bath, so we ordered a brown glass vessel for the boys' bath and went off to shop for counter tops. We immediately honed in on one, an ivory color with sage green and silver in it, turned to each other and said simultaneously: "That would be great in the girls' bath". It was that easy.
All we had to do then was choose a vanity base. It has to be a cabinet so we don't have to touch the tiles which are in excellent shape, but I don't want anything that looks traditional. I've narrowed it down to a couple, both wood in the same tones as the doors and I have a couple of faucets in mind too.
And the ugly medicine cabinet? We're taking it out, patching wallboard in the hole and installing this beauty from Design Within Reach
Today I painted the olive green doors in Benjamin Moore Silver Satin, a bright, grayish white and it has made a huge difference.
If only all remodeling was this easy.
Friday, January 26, 2007
And we've paused
After two days we have wall board up except where the plumbing needs to be changed and we can do no more until that is done, and the window and the tiles have arrived. It would be really nice to get on with things but I'm quite enjoying the nice clean space that's there now. I'm sure I will be really sick of it by the time we start again (mid Feb) but at least we have a jump start.
Until then I will leave you with these photos of the fixtures in the girls' bath that I plan on pulling out.
Wednesday, January 24, 2007
Project Bathroom - we're underway
It feels like we have really started on the bathroom project now, the workers arrived at 8 am and we have a lot of progress already. The electrics have been re-wired to code (GFCI) and in future we shouldn't go bang when we plug in that hairdryer that has been lying in a puddle of water . The new fan/light/nightlight combination is up too, so the contractors will have light to work by. The walls and ceiling have been insulated and the backer board ceiling has been tacked up.
I spent most of the morning on the phone. I checked to see when I could expect delivery of the tiles, and it's a good thing I did. Although my copy of the order form says they had been ordered on January 5th, under one tile sku it says "get from NJ". This was obviously an aide-memoire for them rather than an order, as there was no record in the system. It's been taken care of now, and I should have the whole lot in a week or so. I was a little tigged because I need the wall tiles to take to the cabinet guy so I can choose a co-ordinating top, but Porcelanosa offered to send samples of the tiles by UPS and I should have those in a couple of days. Then I can order the countertop and I think that's it for fixtures.
The plumber called to tell me the toilet I chose is the one nobody has in stock so I can expect a 4-6 week delivery. That should put it right there with the arrival of the window. I asked him to get me a second toilet that we can put in the green bathroom because that thing has a mind of it's own and it's also seriously uncomfortable: low down and round. Apparently that is the best style for potty training little girls but it ain't good for grown-ups. I can see this turning into a "while we're about it" scenario. Once the green toilet is gone, the vanity is going to look old and nasty so we might as well replace it, and obviously you wouldn't put the old faucet back on a new vanity, would you? And we'll need to take the matching green laminate door off the full-length medicine chest.......
The sweetest part of the day? I asked the contractor if he wanted a cheque for part of his estimate now. I expected to pay him a third on agreement of the contract, a third when he starts and a third on completion. His reply? "I have enough to live on, let me get started first." I think we picked the right contractor.
Tuesday, January 23, 2007
It blows
Q) How many trips to X-pooh does it take to buy a bathroom fan?
A) Three.
Trip One: because the contractor wants to start on the electrics tomorrow and then sheetrock the ceiling and I haven't ordered one online yet. I arrived at the "luxury" big box store and asked the Customer Service Rep where they were located. "Oh, I think they are all special order. But you could try through the arch at In-store pick-up". Through the arch there are faucets and hardware and pillows but no ventilation units. An employee asks what I need and it turns out they do have them, just installed last week and hidden behind the faucets with no sign at all. There is one brand, Nutone, six models and they are all ugly. I leave and try three other stores, only one of which carries bathroom fans and that is Hopeless Desperation and they only sell Nutone, but even uglier, less powerful models.
Trip Two: Back to Exasperating to purchase the most energy friendly, least ugly, and most expensive, model.
Trip Three: To return that model and purchase the second most expensive model because that has 4" diameter ducting and the one I had taken home was only suitable for 6" ducting.
Three trips, starting at 2:30 and finishing at 8 pm. I need to go stand under the fan to cool off and in future I must learn to read the box properly before I leave the store.
Monday, January 22, 2007
Shower base chosen, tick.
Settling on a shower base has been the most difficult part of this project. I'd rather chip tiles off the walls for a week than look at any more options that stop water cascading through the ceiling to the shower room below.
So far we have decided on
1) keeping the thirty-eight year old terrazzo base
2) getting a custom-made shower pan, tiled in
i) glass mosaic
ii)mesh-backed pebbles
3) ceramic base
4) acrylic base
5) tiled pan
6) another acrylic pan
We rejected the first once we started the demo, if it looked old and grubby at this point what would it look like with shiny new tiles on the walls and floor? The second had the tile designer and ourselves going crazy trying to find something that went with the other tile choices and the style of the house. The third was Steven's favourite but looked to busy with the mosaic accent wall. The ceramic base was my preference. I wanted something that looked like this
But the cost would be prohibitive and the sizes are European so we'd have to re-frame and there was a long lead time (which at this point wouldn't have mattered but that was before we knew the window would take a trimester to build). I'm determined to have this in the master bath remodel, though. We'll have to make the floor extra waterproof because it's a no-lip system.
Bck to the project in hand. We settled an an acrylic base and then we looked at them and they were all horrible. Cheap feeling and nasty looking. So we went back to plan b. But the thought of a lead pan or a "hot mop" rubber system had me freaking. After all the "hot mop" is the stuff they put on flat roofs and we all know how long that lasts!
Then I walked into Finishing Touches, the local fixture store in Huntington, and told them of my problem, and they showed me an acrylic base that didn't feel like plastic, it felt like ceramic.
It came in a gazillion colours and although it was twice the price of the Kohler looked twice as nice and came in the correct size. And if we install it and find it is too shiny, they sell a teak insert for an only slightly shocking price that looks very zen.
At this stage in the process, money feels like the least of the remodel problems.
Friday, January 19, 2007
(mostly) Excellent service
I spent Tuesday evening online ordering some of the fixtures for the new bath. Shopping around for the best price takes time but beats the hell out of driving round visiting every plumbing supply store and bath showroom in a twenty mile radius to find a Tenso faucet. And that was after I'd visited the Grohe website to locate the dealers. Every one could show my a picture in a catalogue but no one had the model in stock. I'd seen the faucet on the website and had the dimensions but I wanted to see it in real life. I wanted to see how shiny it was, how big, how bulky. After a really frustrating four hours and nearly half a tank of fuel I gave up, came home and started searching online suppliers. By 5:00 pm I had not only ordered the faucet but a matching shower valve trim and a Freehander shower.
Then I moved on to the vessel sink. I'd wanted a bronze tempered glass sink but I was concerned that the color might not be as pictured on the websites and once again I couldn't find anyone locally who had anything in stock - not even the snotty hardware store in Nassau County, NY where the salesman's first question wasn't "Were you looking for glass, ceramic or stone?" but "How big is your budget because we only deal in expensive sinks, we're a high-end store, that's what our clientele demands." (note to self: wear a huge diamond ring and borrow Louis Vuitton bag when shopping in Great Neck). He showed me a bunch of catalogs and gave me a price on a glass vessel that I could beat by $180 elsewhere. Superb customer service.
I identified a cute Italian ceramic vessel sink at Qualiytbath,com, emailed them about lead times, had a reply within 10 minutes saying it would ship 5-7 days after the order was placed, ordered it at 5:30 pm and it arrived by UPS at 3 pm yesterday. Less than 24 hours, free shipping and no sales tax. Oh, and no snotty salespeople of course. I rounded off the evening by ordering the towel racks, toilet roll holders, robe hooks and finally a Toto Maple Softclose Toilet Seat.
Just to prove that I can shop locally without feeling like I'm wasting the salesperson's time, I ventured out again to look at lights and had lots of help from The Lighting Gallery in Huntington. I explained what I was looking for and was directed to contemporary vanity lights. A few questions later and I had the perfect solution: a bar light that won't detract from the mosaic tile but will still make a statement and will fit in with the style of the house. I did have to pay NY sales tax but I got excellent service and I got to feel the merchandise too.
It's all coming together at last. Today, before 9:30 am FedEx dropped off the faucet and shower. The trim is promised, via the wonderful UPS tracking system, for Monday, the other things by the end of the month. The plumber is getting the actual toilet for me and the Grohe shower valve and now he, the handyman, the other contractor, my husband and myself have all agreed on the dimensions of the shower I can go ahead and order the base, safe in the knowledge that five people can't be wrong. Can they?
Friday, January 12, 2007
Custom made
No photos for this post, although there are some links further down.
I finally found someone to make me a floating vanity. Hurrah. I thought this would be a project that the handy guy who likes to work with wood would love but he doesn't have a workshop so he didn't want to do it, although he was happy to mount it on the wall when we found one. My second choice was the trim carpenter but he had never made a cabinet so didn't feel confident.
Let me tell you I'm not asking for anything complicated here: a box 36"w x 22"d x 20"h; three full sides; one stile frame; a bottom; a top with two holes cut out, one for the drain and one for the tap (faucet); two full-overlay doors. That's it.
I even went to IKEA and Kraftmaid with the intention of using an over the refrigerator cabinet but they are 24" deep and it's a tight space. If I had the tools I'm sure I could have sawn 2" off the back of a cabinet and dovetailed it right back on. But never mind.
I then spent hours, days even looking for a vanity that didn't make me want to vomit or run screaming from the store or that was going to cost the price of a holiday in the Bahamas. Nothing. Rien. Nada. Niets.
Then yesterday I was out looking for faucets when I stumbled upon a cabinet maker who will knock me up the box made to my specific dimensions in wood or wenge veneer. He sketched it out as I described it, called it clean, modern and streamlined and said it would take a couple of weeks to knock out. It will have a rolling drawer and a half rolling drawer, so getting to the toiletries will be easy. The wenge sample was gorgeous and looks like this but the unit will look more like this. I will take the tiles in when I get them so I can pick a co-ordinating top in granite or quartz.
And we ordered the window (also custom made from Marvin) so we are almost home............
Tuesday, January 09, 2007
Decisions
We have actually made some actual decisions. Firstly we ordered the tiles from Porcelanosa. The floor and accent wall tiles are the same ones we chose back in October but I decided that the rectified wall field tiles were too classic and so we chose a more contemporary 12"x12" tile that should also be easier to lay.
Then the champion procrastinators finally got down to business and read through the contractors' bids, then phoned them with follow-up questions. It was a no-brainer. The guy we have used before, who does the work himself, who has worked for our neighbors and who we trust to deliver what he was contracted to do was significantly cheaper than the other guy who arrived without a tape measure and sent me to a fictitious plumbing supply store to look at shower bases because "tiled bases always leak". When I asked this guy how he came to his "Basic 8'x 5' Bath" price he told me that because we had done all the demolition ourselves he used the price of a 8' x 7' bath. Now, normally doing the demolition would make the price cheaper (as it was with the contractor we chose) but it seemed here that it was costing us money. Anyway, I really only wanted the tiler who works for this guy, I don't need a GC who pops in every day or so to check on what his guys are doing, and I certainly don't need a flaky GC.
The Marvin window will take four weeks to arrive so no cement board can go in until that's here. In the meantime we will start the electrical update and the plumber will move the vent and pipes and replace the copper waste pipes with PVC. We need to order the rest of the fixtures this weekend and with room for delays we should be done by Steven's birthday in March.
Friday, January 05, 2007
A little more demo
Although we'd agreed we wouldn't tackle the master bath until the boys' bath is finished I got a little bored today and took off the shower doors and hauled them out to the dumpster. Then I took off the door to the medicine cabinet. The one Steven cracked with his elbow oh, nearly twelve months ago. That baby had twelve screws and took me an hour to get off. It also weighed more than the shower doors combined. Still it has now joined them in the dumpster. Unfortunately, I couldn't get the medicine cabinet out as the screws are bent and somebody nailed it in for added strength, so I'm leaving that job for Steven.
I even tried once again to clean the tiles in the shower, now the doors are off it's much lighter in there but, nope, that dirty grout is not getting any cleaner.
My prediction is that by Sunday evening there won't be any tiles, grubby or otherwise in the shower. Now, if I could only find a tiler who is happy to install rectified tiles with 1/16th grout lines...
Thursday, January 04, 2007
Frustration and furry animals
We spent New Year's Day in a fruitless frenzy trying to take down the old media centre/bar in the den. This was my fault. I thought because we had the dumpster we could just knock the baby out and the replace the carpet later. I thought it would be an easy job.
When it came down to it, after we'd spent an hour clearing everything out of and off the bar and then finding new homes for the junk, Steven took a screwdriver to the back of the unit and pronounced it wasn't going to be so simple. Some of the wires for the cable and electrics come out of the floor. The cables that run to the speakers in the other rooms in the house run through the HVAC vents (?!?). In short, he didn't feel confident taking it all to bits and being without a TV or music for days or even weeks.
So reluctantly we cleaned the unit and put all the stuff back.
And then some devil prompted me to wonder again why the was a hole under the light on the unit. We'd thought it was to push the lamp cord through and it would connect to a socket at the back of the unit or even in the basement. But although we'd poked and prodded at it when we first moved in we couldn't find a power source down there so we'd let it go. Now I was curious and we had a tool we hadn't had two year's ago: a flashlight! Steve said he'd run down to the basement if I shone the light and see if he could see it. So I shone it, and then I squinted down the hole.
The following exchange then took place:
Steve: I can't see a light
Modernemama: No, But honey, I know why they drilled the hole.
Steve: Why?
Modernemama: Because they lost their gerbil.
Steve: What are you talking about?
Footsteps up the basement stairs and then he took the torch from me and looked for himself.
Steve: Hmm. I saw that before. I thought it was a shadow.
Modernemama: The shadow of a dead gerbil?
Steve: Sweetie, that's not a gerbil, it's more of a garden rodent.
So now I not only have to live with an ugly media cabinet in the den but also the knowledge that there is a dead rat inside it and the only way I am going to be able to get it out is to demolish the thing once and for all.
And it took me two days to get the speaker cables back in the right order on the stereo receiver (a 1970 Russound model MP3) but at least the iPod is plugged in and we have music throughout the house once again.
Friday, December 29, 2006
More demo
We couldn't do anything else to the boys' bathroom in the way of demolition so we moved on to the laundry room. Actually I take no credit for this, the "we" was all "he". He cleared the room, unsrcrewed the upper cabinets and resorted to the sledgehammer when the were unresponsive. Then he carted it all out to the dumpster, which is now full.
I'd like to clean up the walls and hang new cabinets but he thinks it will be better to wait until the kitchen gets replaced in 2008. My original thought was to do this room and use that s a makeshift kitchen while the big room is being done. But I can see the benefit of waiting - that way we can go throughout the kitchen, mud room and laundry with 18x18" tiles, and get a clean, continuous look.
The only question is whether I can live with a half-demolised laundry room for 20 months.
Santa? No, the demo man
I knew it was only a matter of time before he "personalised" the car but on our own driveway? The morning after he filled the dumpster? How is that possible?
Anyway, the ceiling is now down, we can see where the hole in the flashing round the vent pipe caused the water damage, and the assessment is that it's not too bad. The biggest relief is that there is no longer any smell of mold or rot in the room so I think we can change the cruddier insulation and start putting things back together again.
Next on the list: change the wastepipes to PVC, upgrade the fan to a quieter model, install a light over the shower and a GFCI circuit.
Tuesday, December 26, 2006
The shower pan nightmare
The second good thing was that forty minutes after ringing to enquire about dumpsters (skips) we had one sitting on our drive. And two hours later we had just about filled it.
It was far harder carrying the lumps of broken terrazzo out to the dumpster than it was breaking the shower pan up. That stuff is heavy. But here's the scary bit: the pan was just resting on the floorboards. No plywood reinforcement, no tar-paper or liner. So when you break up the shower base tiny pieces of terrazzo rain down through the cracks in the floorboards onto the bathroom ceiling below. And when you switch on the light in that bathroom you realise that not only does that no longer work, but the fan has stopped also.
Now my problem is that we still have to take up the cement floor tile bed. I imagine that this has a liner because otherwise what stops the mud falling down the spaces between the floorboards? But what if it doesn't? How much debris can I afford to let fall onto the ground floor bathroom before the ceiling collapses? The nightmare continues.....
Monday, December 25, 2006
Xmas Day 2006
Steven stepped up and removed the partition that was preventing us from taking off the last of the wallboard. There's a little mould on the ceiling that was under a piece of framing, but nothing worse. We will experiment with diluted bleach to remove it, but unfortunately there's also a tiny hole in the ceiling where the wood slipped as it was coming out. Whoops.
He is finding that demo is rewarding and kind of fun too. The next job is to try and prise (hammer, drill, jackhammer) the terrazzo shower pan out. We'll see if he's still having fun after struggling with that for a couple of hours.
Wish us luck.